City of Heath Announces Reconstruction, Road Closures on Crisp Lane, Myers Road

by Front Porch Rockwall

 

The City project includes reconstruction of Crisp Lane from Hubbard Drive to Myers Road and Myers Road from Crisp Lane to Terry Lane.

  • The new roadways will be 20-foot wide concrete streets. The roadways will not have curb and gutters.
  • The Crisp Lane pavement has been installed. The contractor is grading the ditches and performing clean-up. Sod will be installed along the roadway within the next few weeks.
  • The contractor has schedule the start of work on the Myers Road roadway culvert crossing beginning Monday, March 4. Myers will be closed to through traffic from March 4 through March 7, weather dependent, in order to install ½ of the culvert crossing.
  • Myers Road will then be open to one-way, south-bound, traffic on March 7 (towards Crisp Lane).
  • The contractor will then construct the other ½ of the culvert crossing and start removing and reconstructing ½ of Myers Road, beginning March 8. The estimated construction time for this portion of the project is 6 to 8 weeks, weather dependent.
  • The contractor for the project is Ed Bell Construction. Their phone number is 214-358-6581.

If you have any questions regarding the project, please contact Chuck Todd, P.E. at 972-961-4885, or ctodd@heathtx.com.

 

 

 

 